When the order finally goes into production we work on a lead time of between 4 and 6 weeks from date of final measurements to time of delivery. During this time period our builders will be preparing the site and taking care of all building works, stripping the old kitchen, plumbing, electrical, tiling and any new walls that might be needed. The builder’s timeline is carefully worked out so that the inconvenience to the client is minimal.
We have found that by using our own builders and taking care of our own project management we are able to avoid almost all the usual disappointments that are so common in the industry.
Installation for an average kitchen is usually 2 to 3 days.Following the installation of the units the Counter tops will then be measured for production.
Our reliable stone suppliers will normally deliver within 3 days from measure, only then can the sinks and hobs get fitted and minor snags attended to. This brings us to the end of the project.